#12LV Switchgear & Motor Control Center (MCC) Checklist
Multi-Asset / Multi-Point Equipment Schedule
Inspect multiple transformers, panels, rooms, motors, or RCDs in this module without overwriting previous assets. Each item receives a permanent QR Sticker UID preserved across annual audits.
Sticker UID: OC-SWIT-9828Standard Limits, Equations & Space Presets
NETA MTS Table 100.18 infrared thermography Delta-T severity classifications, IEC 61439-1 short-circuit breaking capacity verification (Icu >= Ipsc), and NEMA MG-1 phase current balance.
Measured Inputs
Calculated / Evaluated Results
Thermography is graded with the NETA MTS Table 100.18 delta-T criteria; the reference selector switches between comparison with a similar component under the same load and comparison with ambient air.
Pending / Not tested — results stay neutral until valid measured values are entered.
- Pending
Joint Delta T vs Similar Component
- degC
Not tested - 1-3 degC: within normal variation. [NETA MTS Table 100.18]
- Pending
Survey Load Validity
- %
Not tested - enter the measured value. Acceptance: Survey at >= 40% of rated load for a valid thermal comparison [NETA MTS §9 / NFPA 70B]
- Pending
Breaking Capacity Adequacy
-
Not tested - enter the measured value. Acceptance: Icu >= prospective short circuit current at the panel [IEC 61439-1 §10.11]
- Pending
Phase Current Imbalance
- %
Not tested - enter the measured value. Acceptance: Imbalance <= 10% on feeders; motor terminals <= 1% voltage unbalance [NEMA MG-1 14.35 / 14.36]
Verification Checklist (0 / 18)
1Assembly Form of Internal Separation (Form 1, 2b, 3b, 4a, 4b) and IP/IK rating intact with zero missing blanking plates [IEC 61439-2]
2Compartment doors, rotary handle defeat mechanisms, and live busbar safety shutters operate smoothly
3Main and distribution busbar insulators/supports clean, crack-free, and cleared of conductive dust
4Busbar splice joints and cable lug terminations torque-verified and marked with tamper-evident lacquer
5Infrared thermography survey completed through IR windows or open covers at >= 40% rated load [NETA MTS Table 100.18]
6Withdrawable ACB / MCCB cassette racking mechanism (Connected / Test / Disconnected) smooth and padlockable
7Contact resistance (Ductor / micro-ohm) measured across main ACB/MCCB poles within OEM micro-ohm limits
8Electronic trip unit (LSIG) settings verified against the approved protection selectivity study
9Mechanical/electrical interlock between Normal Incomer, Standby Generator Incomer, and Bus-Coupler proven
10MCC withdrawable motor starter buckets, contactors, thermal/electronic overload relays, and VFD cooling fans inspected
11Motor feeder Type 2 coordination (fuse/MCP + contactor + overload relay per IEC 60947-4-1) verified
12Control voltage transformers (CPT), miniature fuses, and door-mounted pilot lamps/meters functional
13Main Protective Earth (PE) busbar continuity and hinged door braided copper bonding straps verified (<= 0.1 Ohm)
14Bottom/top cable gland plates non-magnetic (brass/aluminium for single-core cables) and fire-stopped against vermin
15Anti-condensation space heaters, thermostats, and enclosure louvre fan filters clean and operational
16Arc-flash incident energy label, single-line diagram (SLD), and laminated circuit schedule displayed on panel
17Insulating rubber floor mat (IEC 61111 Class 0/2) placed along full front/rear operating corridor
18Minimum working clearance in front of switchboard maintained unobstructed with zero combustible storage
General Notes